P&O Cruises will not take delivery of its latest newbuild, Iona, until at least August.
In a video update from the Meyer Werft shipyard in Papenburg, Germany, Bernard Meyer revealed the delivery of Iona had been postponed and said they hope they can deliver the ship at the end of August, although could not rule out further delays. The shipyard has already missed two delivery dates of May and July.
Originally due to embark on her maiden voyage to Norway in May, Iona has undergone sea trials and the ship is essentially finished.
The ship successfully transited the Ems river from the Papenburg shipyard to the outfitting facility at Bremerhaven. Initial sea trials were undertaken, which was followed by Iona sailing to Rotterdam to undergo a dry dock inspection. It is unclear what work was carried out during this period. Iona recently embarked on a second round of sea trials off the coast of Norway, and has since returned to Bremerhaven.
The new delay is not good news for Meyer Werft. They only receive the remaining 80% payment after the delivery of the ship has been completed. In the meantime, they are liable for the enormous cost of upkeep, docking and maintenance involved on Iona during the interim, and there is still no guarantee P&O Cruises will accept delivery, until they, themselves, are ready to welcome the ship into their fleet. The shipyard workers also have an interest in the delivery of Iona. Meyer Werft has promised holiday payment totalling 14 million euros, which will only get paid out upon handover of the vessel.
P&O Cruises has currently cancelled all sailings up to 15 October.
As far as I am aware Iona’s maiden cruise was never scheduled for March 2020 but for May 2020. P&O should accept the ship now as she is complete and Carnival Corp. should pay the shipyard what it is owed now.
carnival lost 3.6 billion last 3 months and you want it to pay or a ship that cant sail for months , get realistic
P&O/Carnival Corp are in a legal contract with Meyer’s,they don’t have an option in this matter, unless they want to contest it in a German courtroom.
How likely is it for the rest of the Carnival Group sisterships ordered from both Meyer Werft and Meyer Turku to be built ? Carnival MardiGras has been launched but not completed and Costa Toscana has been started on from Meyer Turku. What is the status of the sister ship to Aidanova at Meyer Werft, and will the follow on ship from Iona be started on ?
AidaCosma is started. First mega block outside Hall if look at webcam. All ships already contracted including Iona’s sister and the rest for Carnival Corp will be built albeit later than planned.
So sad. As if things are not bad enough right now for P&O ?
Bad enough for P&O? Their ship is complete but they are refusing to collect and pay for her! How about Meyer Werft and all the workers?
They can’t collect her. They are under contract. Read the article, the builders are the ones who have delayed delivery.